Which of the following considers time and effort in a project schedule? a.) Mary has only one oven and a small microwave to cook her dishes and warm the guests’ food. b.) Mary's homemade cornbread will be fresher than the cornbread mix that comes in a box from the grocery store. c.) Mary needs to bake the chicken before the cornbread, as the chicken bakes longer and at a different temperature. d.) Mary can bake the chicken in 30 minutes, but the total cooking time is four hours since the chicken has to marinate prior to baking.

Respuesta :

Answer:

D

Explanation:

It considers time because of "30 minutes" and "four hours" in the statement.

Answer:

The statement that considers time and effort in a project schedule is option d.)

Explanation:

"Mary can bake the chicken in 30 minutes, but the total cooking time is four hours since the chicken has to marinate prior to baking."

This statement takes into account the specific cooking time for the chicken as well as the additional time required for marination before baking. It demonstrates an understanding of the sequence of tasks and the time required for each step, which is essential for effective project scheduling.