Answer:
SPEA should have install the new power generator.
Step-by-step explanation:
The information provided is as follows:
Consider the decision tree attached below.
The loss that will be incurred after the generator is installed is, $80,000.
Compute the loss that will be incurred if the generator is not installed as follows:
[tex]E(\text{Loss})=P(HL|P)P(P)\times \$7000000+P(SL|P)P(P)\times \$1000000[/tex]
[tex]=(0.07\times 0.12\times \$7000000)+(0.93\times 0.12\times \$1000000)\\=58800+111600\\=170400[/tex]
The loss that will be incurred if the generator is not installed is $170,400.
The loss from not installing the generator is more than from installing it.
Thus, SPEA should have install the new power generator.