Answer:
$3,927
Explanation:
For the computation of bid price first we need to follow some steps which is shown below:-
Manufacturing overhead rate = Overhead cost ÷ Machine hours
= 45,000 ÷ 100,000
= $0.45
Total manufacturing cost charged to the school
= 2,000 + 400 + (900 × 0.45)
= $2,805
Markup cost = $2,805 × 0.4
= $1,122
Bid price of job = Total manufacturing cost charged to school + Markup cost
= $2,805 + $1,122
= $3,927