Answer:
Mean arrival rate = 0.25 job per hour
Mean service rate = 0.3125 job per hour
Average number of job = 1.85
Average time taken = 7.4 hour
Average number of hours a job received and completed = 10.6 hours
Gubser's welder busy percentage of time = 80%
Explanation:
As per the data given in the question,
Mean arrival rate = 2 ÷ 8 = 0.25 job per hour
Mean service rate = 1 ÷ 3.2 = 0.3125 job per hour
Average number of job = (Mean arrival rate^2 × Standard deviation^2 + (mean arrival rate ÷ mean service rate)^2) ÷ 2(1 - (mean arrival rate ÷ mean service rate)^2)
= (0.25^2 × 2^2 + (0.25 ÷ 0.3125)^2) ÷ 2(1-(0.25 ÷ 0.3125))
= 0.25 + 1.60
= 1.85
Average time taken by job waiting = Average number of job waiting ÷ Mean arrival rate
= 1.85 ÷ 0.25
= 7.4 hours
Average number of hours a job received and completed = Average time taken by job waiting + 1 ÷ Mean service rate
= 7.4 + 1 ÷ 0.3125
= 10.6 hours
Gubser's welder busy percentage of time = Mean arrival rate ÷ Mean service rate
= 0.25 ÷ 0.3125
= 0.80
= 80%