Rotan Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below:

Hours
Move time 3.2
Wait time 10.9
Queue time 5.1
Process time 1.2
Inspection time 0.2
The throughput time was:

A) 20.6 hours

B) 16 hours

C) 4.6 hours

D) 9.7 hours

Respuesta :

Answer:

D) 9.7 hours

Explanation:

It is a time period which is taken to manufactured the product

The computation of the throughput time is shown below:

= Move time + Queue time + Process time + Inspection time

= 3.2 + 5.1 + 1.2 + 0.2

= 9.7 hours

It is a combination of the move time, queue time, process time, and the inspection time.

All other information which is given is not relevant. Hence, ignored it