A car manufacturer has just implemented a new Master Production Schedule (MPS) to manage production over the next three months. Which of the following is NOT typically included in a Master Production Schedule? O Production rate for each week and day O Specific production targets for each product line O Supplier delivery schedules for critical components O Detailed demand forecasting for the upcoming fiscal year