XYZ Company has 10 workers per shift who areworking 3 shifts per day. Their breaktime is 75 minutes / shift. The rate of output for Product 001 is 50pcs/hr. They are working 5 days a week and consider 4 weeks in a month. 1. Compute the max cap for 1 month 2. 3 workers of 1st shift are absent due to covid beginning Day 2 of 3. What is the available capacity in Week 2 if power failure occurred from 10 pm to 11:45 pm of Day 3 4. On day 4 and 5 of Week 4, all the workers will undergo training from 8 am to 5 pm. Find the available capacity in that entire month. 5. The client wants you to deliver 960,000 pcs of Product 001 in one month but the following occurred, 2 workers of 1st shift rendered half day while 3 workers of 2nd shift were absent for 3 days. Will you accept the requirement of the client?