When developing project networks, which of the following is not a reason for delineating technical dependencies first before doing resource dependencies?
A. Even if resources are known, one cannot assess the impact of limited resources until a resource-neutral schedule is created.
B.All of these alternatives are reasons for delineating technical dependencies first before doing resource dependencies.
C.Resource availability may not be known until the initial schedule is completed.
D.An effort to examine the interactions between technical/logical constraints and resource limitations frequently uncovers surprising problems.
E.The interrelationships and interactions among time and resource constraints are complex for even small project networks.